Patience and Building Time
When
scratch-building a model, this is roughly how my time breaks down across the
project. This assumes the plans are ready to use so I am counting only the
time required to actually build the model.
Planning |
When scratch building, planning is part of the design process. When
building from a kit (or plans), reading the instruction, reviewing the
plans, laying out the radio and engine installation and other modifications
amounts to 5-10% of the time spent on the project. |
Parts fabrication |
~ 15 - 20% |
Aligning, fitting and adjusting parts |
~ 25% |
Radio/Engine installation and adjustment |
~ 5 - 10% |
Gluing |
~ 2% |
Prep for finish and finishing |
~ 40 - 50% |
|
|